The Pennsylvania Department of Transportation (PennDOT) District 11 resumed major road work at the intersection of Mayview Road and Boyce Road in South Fayette Township on March 1, 2022. Work will include replacing a culvert, adding turn lanes and making design improvements.
The landslide area on Mayview Road near Hastings was opened before the Boyce-Mayview closures begin.
Closures and detours will occur until work is completed around November 8, 2022. There are two alternating closure combinations.
Local traffic will be able to access homes and businesses in the closure areas using the detour routes; however, local access through the Boyce-Mayview intersection will not be allowed.
Initially, Pennsylvania American Water will complete water line work, including installation of a 36-inch line underneath Boyce Road.

SCHEDULE OF WORK, DETOURS AND CLOSURES
These are the planned closures and detours, according to PennDOT. All dates are approximate.
March 1 – March 11 (Water Line Work)
- Closure (around-the-clock) of western leg of Boyce Road (Washington Pike side) and southern leg of Mayview Road (Cecil side)
- March 11 - Open western leg of Boyce Road and southern leg of Mayview Road
Friday, March 11 – Sunday, April 3 (Water Line Work) - DATES ARE APPROXIMATE AND WILL BE UPDATED BASED ON UPDATES FROM PENNDOT
- Closure of eastern leg of Boyce Road (Route 19 side) and northern leg of Mayview Road (Hastings side)
- Detour from EAST of the intersection
- Take Boyce Road to Washington Pike
- Turn right onto Washington Pike (Route 3003)
- Washington Pike becomes Washington Avenue (Route 50)
- Turn right onto Bower Hill Road
- Turn right onto McLaughlin Run Road
- For detour to Mayview Road, turn right onto Lesnett Road and follow to Mayview Road – end detour
- For detour to Boyce Road, continue straight on McLaughlin Run Road to Route 19 (Washington Road)
- Take the ramp to South 19
- Follow southbound Route 19 to Boyce Road
- End detour to Boyce Road
- Detour from WEST of the intersection
- Take Route 19 (Washington Road) at Boyce Road northbound
- Take the ramp to McLaughlin Run Road
- Turn right onto McLaughlin Run Road toward Bridgeville
- For detour to Mayview Road, turn left onto Lesnett Road and follow to Mayview Road – end detour
- For detour to Boyce Road, continue straight on McLaughlin Run Road
- Turn left onto Bower Hill Road
- Turn left onto Washington Avenue (Route 50)
- Washington Avenue becomes Washington Pike (Route 3003)
- Follow Washington Pike to Boyce Road
- End detour to Boyce Road

Sunday, April 3
- Opening of the eastern leg of Boyce Road and northern leg of Mayview Road - DATES ARE APPROXIMATE AND WILL BE UPDATED BASED ON UPDATES FROM PENNDOT
April 3 – August 22: Road / Bridge Work (DATES ARE APPROXIMATE AND WILL BE UPDATED BASED ON INFORMATION FROM PENNDOT )
- Closure of western leg of Boyce Road (Washington Pike side) and southern leg of Mayview Road (Cecil side)
- Detour from NORTH of the intersection
- Take Mayview Road to Lesnett Road (Route 3034)
- Turn right onto Lesnett Road
- Turn left onto McLaughlin Run Road
- Turn left onto Bower Hill Road
- Turn left onto Washington Avenue (Route 50)
- Washington Avenue becomes Washington Pike (Route 3003)
- (Western Leg of Boyce Detour Ends)
- Washington Pike becomes Morganza Road in Washington County
- Turn left onto Georgetown Road (Route 1010)
- Follow Georgetown Road back to Mayview Road
- (Southern Leg of Mayview Road detour ends)
- Detour from SOUTH of the intersection
- Same detour in the opposite direction

August 22
- Opening of western leg of Boyce Road and the southern leg of Mayview Road
August 22 – November 8 (Road / Bridge Work) - DATES ARE APPROXIMATE AND WILL BE UPDATED BASED ON UPDATES FROM PENNDOT
- Closure of eastern leg of Boyce Road (Route 19 side) and northern leg of Mayview Road (Hastings side)
- Detour from EAST of intersection
- Take Boyce Road to Washington Pike
- Turn right onto Washington Pike (Route 3003)
- Washington Pike becomes Washington Avenue (Route 50)
- Turn right onto Bower Hill Road
- Turn right onto McLaughlin Run Road
- For detour to Mayview Road, turn right onto Lesnett Road and follow to Mayview Road – end detour
- For detour to Boyce Road, continue straight on McLaughlin Run Road to Route 19 (Washington Road)
- Take the ramp to South 19
- Follow southbound Route 19 to Boyce Road
- End detour to Boyce Road
- Detour from WEST of intersection
- Take Route 19 (Washington Road) at Boyce Road northbound
- Take the ramp to McLaughlin Run Road
- Turn right onto McLaughlin Run Road toward Bridgeville
- For detour to Mayview Road, turn left onto Lesnett Road and follow to Mayview Road – end detour
- For detour to Boyce Road, continue straight on McLaughlin Run Road
- Turn left onto Bower Hill Road
- Turn left onto Washington Avenue (Route 50)
- Washington Avenue becomes Washington Pike (Route 3003)
- Follow Washington Pike to Boyce Road
- End detour to Boyce Road

November 8
- Opening of all legs of Boyce Road and Mayview Road
About the Boyce-Mayview Project
- Project by Pennsylvania Department of Transportation to improve intersection and help control flooding
- Prime Contractor: Frank Gavlik & Sons, Inc.
- Improvements include:
- Installation of left turning lanes in each direction from Boyce Road to Mayview Road
- Addition of right turning lane from northbound Mayview Road to eastbound Boyce Road
- Culvert/bridge replacement on Mayview Road over a branch of Chartiers Creek
- Roadway widening
- Lighting improvements
- Intersection realignment
- Updated traffic signal hardware
- Drainage improvements
- Stream channel realignment
- Guide rail improvements
- Milling and Paving
South Fayette Township is not involved in this work and is providing this information as a courtesy. We update this information based on information received from PennDOT.